East Med is a Pipe Dream
Cemal ASLAN
While the Leviathan could have some positive regional impacts, talk of the Eastern Mediterranean becoming a major source of European energy is similarly overblown. The EastMed pipeline;The project is ambitious, enormous and – at least today – probably unnecessary.
The EU Commission selected the Eastern Mediterranean Pipeline as a “project of common interest,” warranting it further study. The pipeline would run from Cyprus to Crete and then to continental Europe. EU officials are attracted to the idea because it would allow Europe to slash its dependence on Russian gas, and with Greece’s economy mired in deep depression, the East Med Pipeline could be viewed as an economic development project for Southern Europe. However, there are several reasons this project won’t move beyond the dream phase. First, building a pipeline over such a vast distance, and through deep Mediterranean waters, would be prohibitively expensive. The pipeline from Cyprus to Crete alone could cost $20 billion. Second, the politics are dreadfully complicated. The longstanding division of Cyprus stands in the way of a cheaper pipeline route through Turkey. In fact, Turkey flatly objects to the development of gas in Cypriot waters, which it does not recognize—a dynamic that won’t change anytime soon.
At first glance the EastMed is an impressive idea. The pipeline would transport 10 billion cubic metres per year (Bcm/y) of gas from eastern Mediterranean gas fields to Greece and Italy. About 1900km long, and reaching depths below 3km, it would be the world’s longest and deepest subsea pipeline. The estimated cost is 7 billion €’s.
But for those who follow European energy security, Monday’s ceremony brought a kind of déjà vu. It was difficult not to remember a similar ministerial ceremony that took place in Vienna in June 2006, proclaiming next steps for the Nabucco pipeline.
The two projects have many similarities: huge gas transit capacity; long pipelines; connections between Europe and multiple gas supply sources (in the case of Nabucco, Azerbaijan, Turkmenistan, Iran and Iraq). Both were also predicted to be costly, although the EastMed pipeline is even more expensive than Nabucco’s €5 billion initial estimated price tag. And in both cases, energy ministers and the European Commission promised that the project would contribute not only to the security of Europe’s gas supply, but also to wider regional cooperation.
As we know, the story of Nabucco did not have a happy end. The project soon proved to be more of a pipe dream than a realistic pipeline project.
East-Med Pipe line: Is it really a feasible project.?
So the question now is whether the EastMed pipeline is really a feasible project Or is it just more wishful thinking from the EU?
The answer to this question is not simple, but the EastMed plan sounds not convincing.
Preliminary feasibility studies claim that the project is viable both technically and commercially. However, these studies make a double bet on future gas trends in the region. On the demand side, they assume a substantial increase in EU gas import requirements. On the supply side, they predict that large amounts of eastern Mediterranean gas will become available for export to Europe.
The first bet looks reasonable, albeit with a caveat. The EU’s gas import requirements are likely to grow in the future, partly due to rapidly declining domestic production. However, this does not necessarily mean that eastern Mediterranean gas will be best positioned to fill the gap. At the end of the day, cost competitiveness will be key. Will Europe satisfy its growing requirements with eastern Mediterranean gas, or simply by increasing deliveries from Russia and other traditional suppliers?
The second assumption, that the eastern Mediterranean is sure to become a major exporter, is even more doubtful. Over the last years various challenges have revealed the limits of the region’s gas potential: continuous investment decision delays in Israel; downward revisions of gas resources in Cyprus; major gas shortages in Egypt.
In fact, only the 2015 discovery of the large-scale Zohr gas field in offshore Egypt, the largest discovery in the Mediterranean, could revitalise the outlook. But Egypt is not interested in the planned EastMed pipeline, having at its disposal two large liquified natural gas (LNG) facilities that currently sit idle. And even if regional gas production accelerates, domestic demand might limit export potential. Egypt’s gas demand is set to rise from the current 50 Bcm/y to around 70 Bcm/y in 2030. Israel expects its gas demand to quadruple by 2040.
In short, the gas export potential of the eastern Mediterranean is still not clearly defined, and it will also depend on domestic gas demand.
With all these uncertainties, it seems premature to discuss such a large and costly project as the EastMed pipeline. EastMed could make sense in years to come, once European gas dynamics and the real export potential of the eastern Mediterranean become clearer. But for the time being it looks like another EU fantasy.
A more reasonable option for the eastern Mediterranean region would be joint use of the existing Egyptian LNG facilities. Indeed, the geographical proximity of Egyptian, Israeli and Cypriot offshore gas fields could well allow coordinated development. This might create the economies of scale needed to make the first gas exports from the eastern Mediterranean region competitive.
Such an approach would also offer eastern Mediterranean gas suppliers flexibility in terms of destination markets. For instance, through Egyptian LNG terminals, these fields could also serve the rapidly growing Turkish market – and not just southern Europe, as would be the case with the EastMed pipeline. Furthermore, a joint regional export scheme via the Egyptian LNG facilities could also provide a first opportunity to test commercial gas cooperation between Egypt, Israel and Cyprus.
If successful, this cooperation could then eventually scale-up in the 2020s, if new gas resources are found in the region and gas demand justifies the construction of additional infrastructure. Only then would it be worth considering grand projects like the EastMed gas pipeline.
Strengthening LNG options
There are several LNG alternatives for the Leviathan. An LNG terminal in Cyprus has been looked at. This would allow for more flexibility than a long-distance pipeline and is probably the most economical route for large-scale gas exports. However, the site location at Vassilikos is small, raising engineering questions. Furthermore, Israel wants to ensure it maximizes export revenues and can properly manage the facility’s security, making a terminal outside of Israeli territory unlikely. An alternative is an LNG facility within Israel, but environmental opposition, interference with tourist destinations, and competition for space with container ports present challenges to this approach.
Limited Energy Hub
The development of the Leviathan, which is again inching forward now that the Israeli government is settling its differences with Noble Energy and Delek Group, could be a significant milestone for the region. It will introduce a very large source of natural gas for Israel and its neighbors, providing an economic boost while offering potentially positive (although largely theoretical) geopolitical benefits. But talk of a larger “game changer” with the Leviathan is quite clearly overstated. Energy trade can contribute to positive cooperation, but it is unlikely to single-handedly transform the longstanding points of conflict between Israel and its neighbors. Furthermore, exports to Europe are questionable, if not unlikely. A pipeline is too expensive, and LNG export terminals face technical challenges, not to mention long lead times. As a result, offshore gas in the Eastern Mediterranean will likely remain a regional story, rather than a global one.